A new telehouse is being built. The work began in November.
It was difficult to remove the old mast. Therefore, rockbreakers were used. The old water pipes caused problems.
Underground work takes a lot of time. The cornerstone will be laid halfway through the project.
The construction does not disturb journalists. Colleagues are supportive.
Unexpected things happened during construction. For example, a cable was drilled. It interrupted electricity for 12 hours.
Due to the construction, there are disturbances for the city residents. Dust and large machinery hinder traffic.
The telehouse will be completed ahead of schedule.